Hi Dan,

Regarding the access, there are no additional requirements except to confirm that sight distance was addressed with trimming of the tree. As far as TIA, ODOT recommend that the share access be included if the City requires one. I don’t think we need to meet prior to the PreApp unless you would like to.

Thanks,

From: Dan Zinder <dzinder@cityofmolalla.com>

Sent: Wednesday, October 6, 2021 8:52 AM

To: DANIELSON Marah B <Marah.B.DANIELSON@odot.state.or.us>; TAYAR Abraham <Abraham.TAYAR@odot.state.or.us>

Cc: Mac Corthell <mcorthell@cityofmolalla.com>; Gerald Fisher <gfisher@cityofmolalla.com>; Sam Miller <smiller@cityofmolalla.com>

Subject: PRE16-2021 - Colima Apartments Phase II

 

This message was sent from outside the organization. Treat attachments, links and requests with caution. Be conscious of the information you share if you respond.

Marah and Avi,

Touching base before tomorrow’s pre-app with Colima Apartments. Will ODOT be recommending additional improvements to the access or turn lanes as a result of this project? Generally want to get a sense if anything changes from the first phase with the additional units. We can schedule a time to discuss, if/as needed.

Best,

Dan Zinder