From: Gerald Fisher
Sent: Fri Apr 23 11:29:10 2021
To: 'Andrew Johnson'
Cc: Mac Corthell; Sam Miller; Dan Zinder
Subject: RE: PRE06-2021 - 820 W Main ST Follow Up
Importance: Normal
Attachments: image001.png; Hi Andrew, The following is an estimate based on when you will be able to get planning approvals and move forward with building plan submittals. The transportation SDC numbers are based on our estimate of the City Council’s SDC update which will be less than the original approved SDC’s set back in 2020. Water SDC (2” water meter) = $22,217 Water SDC (1” irrigation meter) = $6,944 note this is optional but recommended due to sewer fees without irrigation meter. Sewer SDC = $59,711 Stormwater SDC = $8,325 Transportation SDC = $251,958 Parks SDC = $0 (Exempt) Total SDC = $349,155 Regards, Gerald Fisher, P.E. | Public Works Director City of Molalla 117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038 Office: 503.829.6855 | Direct: 503.759.0218 CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you. From: Andrew Johnson <ajohnson@INSITEREALESTATE.com> Sent: Friday, April 23, 2021 8:26 AM To: Dan Zinder <dzinder@cityofmolalla.com> Cc: Mac Corthell <mcorthell@cityofmolalla.com>; Gerald Fisher <gfisher@cityofmolalla.com>; Sam Miller <smiller@cityofmolalla.com> Subject: RE: PRE06-2021 - 820 W Main ST Follow Up Dan - Thank you for forwarding. We’re in the process of revising our site plan based on the comments discussed yesterday. We’ll review the documents you sent and let you know if we have any questions or concerns. Gerald – As discussed yesterday, below is a summary of the impervious area for the site:
Please let me know what SDC’s we can expect to be charged.
If anybody has any questions or concerns for us, please don’t hesitate to reach out.
Thank you,
Andrew
Andrew Johnson, P.E.
Project Manager
Direct: 630-617-9124
Mobile: 847-287-9292
From: Dan Zinder <dzinder@cityofmolalla.com>
Sent: Thursday, April 22, 2021 6:50 PM
To: Andrew Johnson <ajohnson@INSITEREALESTATE.com>
Cc: Mac Corthell <mcorthell@cityofmolalla.com>; Gerald Fisher <gfisher@cityofmolalla.com>; Sam Miller <smiller@cityofmolalla.com>
Subject: PRE06-2021 - 820 W Main ST Follow Up
Hi Andrew,
Good to meet with you today. Please find our planning procedures document attached. The Building Orientation and Design sections (17-3.2.040) addresses architectural standards and also Feel free to reach out to me with Qs as you approach submittal.
I’ve also included a link to the Planning Commission packet for the Cascaded Center approvals:
And attached the landscaping plan.
Best,
Dan Zinder
Associate Planner, City of Molalla
117 N Molalla Ave | PO Box 248
Direct: 503.759.0226 | Office: 503.829.6855