From: Sam Miller

Sent: Tue Sep 28 14:04:59 2021

To: 'artemy efimoff'

Subject: RE: BP26-2021 is ready for pickup / 829 E 5th St.

Importance: Normal

 

It is

From: artemy efimoff <artye79@gmail.com>

Sent: Tuesday, September 28, 2021 1:52 PM

To: Sam Miller <smiller@cityofmolalla.com>

Subject: Re: BP26-2021 is ready for pickup

Hi Sam.

Is this in reference to 829 5th St?

On Tue, Sep 28, 2021, 12:45 PM Sam Miller <smiller@cityofmolalla.com> wrote:

Good Afternoon Artemy,

I have not seen that you have submitted a Public Works ROW Permit (for review and approval), along with the payment for connection and SDC fees. Certificate of Occupancy will not be issued until all improvement have been completed per conditions of approval and accepted by the City. Please reach out to me if you have any questions.

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com

From: artemy efimoff <artye79@gmail.com>

Sent: Wednesday, September 15, 2021 11:47 AM

To: Sam Miller <smiller@cityofmolalla.com>

Subject: Re: BP26-2021 is ready for pickup

Good morning Sam

Will come by early on next week too pick up the permit.

Thanks.

On Tue, Sep 14, 2021, 4:51 PM Sam Miller <smiller@cityofmolalla.com> wrote:

Hi Artemy,

Follow up with Dan’s email. I’m including Permit and Connection fees along with the Public Works ROW Permit. Let me know if you have any questions pertaining to either of these. Thanks

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com

From: Dan Zinder <dzinder@cityofmolalla.com>

Sent: Tuesday, September 14, 2021 1:00 PM

To: artemy efimoff <artye79@gmail.com>

Cc: Julie Larson <jlarson@cityofmolalla.com>; Sam Miller <smiller@cityofmolalla.com>

Subject: BP26-2021 is ready for pickup

Hi Artemy,

Your building permit authorization is ready for pickup. I’ve attached the SDCs, payment for which will be required upon pickup, and public works conditions. These conditions accounted for the potential of directing water across a new easement. Otherwise a dry well will be required. We’ll prepare a connection fee summary as well for you. These fees will be roughly $1300 and often times builders prefer to pay them in conjunction with SDCs.

Also, your property will need to be addressed as it currently has none. Next in sequence will be 829 E 5th ST and I can send the form for that after payment/pickup.

Best,

Dan Zinder

Associate Planner, City of Molalla

117 N Molalla Ave | PO Box 248