From: Gerald Fisher

Sent: Wed May 19 13:14:52 2021

To: Dan Zinder; ODOT Region 1 Develoment Review (ODOT_R1_DevRev@odot.state.or.us); Marah Danielson - ODOT (marah.b.danielson@odot.state.or.us); Mike Penunuri

Cc: Sam Miller; Mac Corthell; Julie Larson

Subject: RE: Comments Requested for Molalla Planning File SDR02-2021 - 525/535 W Main ST - Scandia/ICL

Importance: Normal

Attachments: 20210519 525-535 W Main - Scandia Conditions of Approval (SDR02-2021).pdf;

 

Hi Dan,

Here are my comments. Since there were no triggers there are no SDC’s for this project.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Dan Zinder <dzinder@cityofmolalla.com>

Sent: Tuesday, May 18, 2021 4:23 PM

To: Gerald Fisher <gfisher@cityofmolalla.com>; Mike Penunuri <penunuri@molallafire.org>; ODOT Region 1 Develoment Review (ODOT_R1_DevRev@odot.state.or.us) <ODOT_R1_DevRev@odot.state.or.us>; Marah Danielson - ODOT (marah.b.danielson@odot.state.or.us) <marah.b.danielson@odot.state.or.us>

Cc: Sam Miller <smiller@cityofmolalla.com>; Mac Corthell <mcorthell@cityofmolalla.com>; Julie Larson <jlarson@cityofmolalla.com>

Subject: Comments Requested for Molalla Planning File SDR02-2021 - 525/535 W Main ST - Scandia/ICL

All,

Comments are requested for a site design review for 525/535 W Main ST by 6/2/2021. Please let me know if you will need additional time.

A couple of FYIs -

The Applicant did not include the waterline and easement from the original submittals on their revised plans arguing that it was not a completeness item. Mac and I discussed the new waterline and easement and agreed with that determination. It can, however, be a finding/condition that the existing system is substandard and needs to be replaced w/ the appropriate easement.

Also, AKS researched the sewer easement on Avison’s property and unfortunately this is another case where the document was finished but never recorded. We will have to condition the easement as part of this process.

Best,

Dan Zinder

Associate Planner, City of Molalla

117 N Molalla Ave | PO Box 248

Direct: 503.759.0226 | Office: 503.829.6855