From: Sam Miller

Sent: Tue May 25 15:22:38 2021

To: Gerald Fisher; Tracy Evans

Subject: RE: 1441 W. Main - sewer connection

Importance: Normal

 

Hello Tracy,

Permit, connection and SDC fees have been paid. The only thing I’m missing is the decommissioning certificate for the septic tank from the County. Please have your plumber provide certification soon as. Thanks

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com

From: Gerald Fisher <gfisher@cityofmolalla.com>

Sent: Tuesday, May 25, 2021 12:41 PM

To: Tracy Evans <tracylee2068@gmail.com>

Cc: Sam Miller <smiller@cityofmolalla.com>

Subject: RE: 1441 W. Main - sewer connection

Hi Tracy,

I’ve included Sam in this and he should be able to answer if all of the permit and connection fees were paid and the decommissioning certificate was received. I’ve confirmed that the system development charges were paid in 2019. Thanks.

Hi Sam,

Can you let Tracy know if we are good on the sewer permitting side of things? Thanks.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.

From: Tracy Evans <tracylee2068@gmail.com>

Sent: Tuesday, May 25, 2021 10:22 AM

To: Gerald Fisher <gfisher@cityofmolalla.com>

Subject: 1441 W. Main - sewer connection

Hi Gerald,

We spoke and emailed months ago about the property at 1441 W. Main. I am excited to announce as of June 1st the place will be ours.

I wanted to circle back before the name changes on the account that everything needed for the hook up of sewer and decommissioning of the septic is complete. We hired someone to do that a couple weeks ago and it all looks good on our side.

Teresa Evans