From: Kelly Richardson

Sent: Mon Jul 30 10:13:14 2018

To: Aldo Rodriguez

Cc: Gerald Fisher

Subject: FW: 309/311 E 5th St

Importance: Normal

Attachments: image001.jpg;

 

Aldo & Gerald

I have been attempting to help this person with her questions. She is wanting to know the costs involved for a complete tear down and rebuild of this duplex. Not necessarily the permit costs just any additional costs from the city.

Is there any type of review or application necessary for this project. Is there anything in additional costs regarding city services water/sewer is there any costs regarding SDC up charge or not.

I was able to locate the lot and get basic information off of the County website however on the tax information they say the address doesn’t exist.

Or anything I didn’t list,

Thank you,

Kelly Richardson, CMC

City Recorder / City of Molalla

117 N. Molalla Ave. / P.O. Box 248 / Molalla, OR 97038

503-759-0291 Direct / 503-829-3676 Fax

imagePUBLIC RECORDS LAW DISCLOSURE

This email is a public record of the City of Molalla, Oregon and is subject to public disclosure unless exempt from disclosure under Oregon Public Records Law. This email is subject to the State Retention Schedule.

CONFIDENTIALITY NOTICE

This e-mail message contains confidential information belonging to the sender or receiver. The information in this message is intended for the addressee’s use only. If you are not the intended recipient you are hereby notified that you are prohibited from reading, using, disclosing, copying, or distributing this information in any way; further, you are prohibited from taking any action based upon the contents of this e-mail. If you have received this e-mail by mistake, please delete it immediately. For further questions call our office at 503-759-0291.

From: Esther Kirk <sjkirk@molalla.net>

Sent: Monday, July 30, 2018 8:14 AM

To: krichardson@cityofmolalla.com

Subject: 309/311 E 5th St

Kelly,

What I want to do is to use the same footprint and floor plan as the existing building. Since it will be exactly the same, but a nicer, more modern building, there should be no SDC fees.

Esther Kirk