From: Steve Ward
Sent: Fri Feb 19 07:03:30 2021
To: Gerald Fisher; Mac Corthell
Cc: Rob Justus (rob@hfdpartners.com); 'Doug Circosta'
Subject: Molalla Water
Importance: Normal
Attachments: 20210219070011762.pdf; Gerald, As discussed earlier this week, please see the attached. We would propose running a new public W/L (shown in red) about half way down the property and then stubbing to the west for future connection. The WM(s) would also be mid-point on the property (shown in blue). Preliminary calculations show we need either 2-2” WM’s or 1-3” WM to serve the site. This is based upon having good pressure at the site which we know is true. Can you please tell us the SS and Water SDC’s are for 2-2” WM’s vs 1-3” WM. Thank you for your assistance. Steven A. Ward PE Westech Engineering Inc. 3841 Fairview Industrial Drive SE Suite 100 Salem, OR 97302 Office 503-585-2474 Mobile 503-931-3460