From: Dan Zinder

Sent: Mon Sep 14 12:35:41 2020

To: Gerald Fisher

Cc: Sam Miller

Subject: Re: 501 E Main Laundromat to C-store

Importance: Normal

 

Gerald,

 

Do you have additional comments for the Applicant regarding Pre-App 11-2020? I imagine that we'd want the sewerage line to come in from E Main.

 

I'm trying to decide what to do with this pre-app. I had tentatively rescheduling for this Thurs but want to make sure that there can be PW participation. If we have to postpone, I'll get the applicant what we have and have ODOT submit written comments as they can.

 

Best,

Dan Z

 

 


 

From: Gerald Fisher

Sent: Thursday, September 3, 2020 11:27:05 AM

To: Dan Zinder

Cc: Dan Huff

Subject: 501 E Main Laundromat to C-store

Hi Dan,

Assuming that the laundromat is 5,500 SF then the SDC’s for a new laundromat would be $193,098. The SDC’s for a new C-store of the same size is $1,014,641. The SDC’s to convert the laundromat to a C-store is $821,543. There are no waivers in place for any kind of change in use. The laundromat was active when the TSP update was done so those trips were counted and can be credited to the C-store conversion. However, the trips generated from a C-store have a larger impact to the transportation network than a laundromat which is why the cost of those impacts are so high.

Regards,

Gerald Fisher, P.E. | Public Works Director

City of Molalla

117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038

Office: 503.829.6855 | Direct: 503.759.0218

CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.