From: Sam Miller
Sent: Tue Aug 17 17:16:20 2021
To: srsmelser@gmail.com
Subject: RE: Legal Forms for 150 Miller Project
Importance: Normal
Good Afternoon Steve,
Following up with our conversation from earlier today.
I will need the following for plan review before we can move forward with permitting:
Once plans have been approved, and prior to issuing the construction permit, city requires a performance bond of 125% of the design engineer estimate, insurance for the construction work, remaining 3.5% construction permit fee of the final estimated cost to construct, and hold a preconstruction meeting. Let me now if you have any question.
Regards,
Sam Miller | Sr. Engineer Tech.
City of Molalla
117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038
T : 503-759-0217 | E: smiller@cityofmolalla.com
From: Mac Corthell <mcorthell@cityofmolalla.com>
Sent: Monday, August 16, 2021 1:57 PM
To: Sam Miller <smiller@cityofmolalla.com>; srsmelser@gmail.com
Subject: Legal Forms for 150 Miller Project
Hi Mr. Smelser,
After speaking with our PW Director, it seems I was unaware of the process that’s already in place. You will work with Sam Miller (cc’d) to get the Right of Way Dedication, Public Utility Easement, and Waiver Against Remonstrance taken care of. Thank you.
Sincerely,
Macahan “Mac” Corthell, J.D. | Planning Director
City of Molalla
117 N Molalla Ave. | PO Box 248 |Molalla, OR 97038
Phone - 503.829.6855
Fax – 503.829.3676
Email – mcorthell@cityofmolalla.com
Website – http://www.cityofmolalla.com
CONFIDENTIALITY NOTICE: The information contained in this email message, including any attachments, is for the sole use of the intended recipient(s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is prohibited. If you are not the intended recipient and have received this communication in error, please contact the sender by reply email and destroy all copies of the original message. Thank you.