I’ve attached the additional info on pipe material. Staking for the Water and Sanitary services has been requested. We hope to move in Monday the 29th. Tentative schedule below:

Week of 11-29 Move-in, Sanitary Lateral, Water Service, (weather & staking permitting)

Week of 12-6 Roadway Excavation & Base Rock (weather permitting)

Week of 12-13 Curb & Gutter (weather permitting)

Thanks,

Roy Bonner

Jim Smith Excavating

From: Sam Miller [mailto:smiller@cityofmolalla.com]

Sent: Tuesday, November 23, 2021 12:25 PM

To: Roy Bonner <roy@jimsmithexcavating.com>

Subject: RE: 150 Miller Street Material Submittals

Hi Roy,

Email will be fine. I will also need your schedule for construction and do you have a start date in mind?

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com

From: Roy Bonner <roy@jimsmithexcavating.com>

Sent: Tuesday, November 23, 2021 12:00 PM

To: Sam Miller <smiller@cityofmolalla.com>

Subject: RE: 150 Miller Street Material Submittals

Hi Sam,

I will get the pipe material items asap. The asphalt and concrete will be later. Is an email copy of those items acceptable?

Thanks

Roy Bonner

Jim Smith Excavating

From: Sam Miller [mailto:smiller@cityofmolalla.com]

Sent: Tuesday, November 23, 2021 11:32 AM

To: Roy Bonner <roy@jimsmithexcavating.com>

Cc: Steve Smelser <srsmelser@gmail.com>

Subject: 150 Miller Street Material Submittals

Good Afternoon Jim,

See Attached for your records, still missing a few submittal items

 

Let me know if you have any questions. Thanks

Regards,

Sam Miller | Sr. Engineer Tech.

City of Molalla

117 N Molalla Ave. | PO Box 248 | Molalla, OR 97038

T : 503-759-0217 | E: smiller@cityofmolalla.com