Composting Shortened Schedule – August Special EQC

Note: all significant documents must be reviewed and approved by Obrien, Emer, Communications (Susan Mills), Goldstein

Note: Lee should contact all document reviewers now to have them reserve time on their schedules for document review – Emer normally requires two weeks for review; someone will have to talk to her about this schedule

Event/Action

Date

Owner

Notes

Complete rulemaking planning form

ASAP

Obrien – review and approval by Emer required

 

Obtain leadership team approval of planning form

Upon completion by Obrien

Goldstein

 

Schedule proposed AC dates, reserve rooms

ASAP

Lee

 

Complete AC membership approval memo for director

ASAP

Lee/Obrien

 

Submit AC membership approval memo to director

When received from Lee/Obrien

Goldstein

 

Start drafting AC documents: Agenda, Fiscal Impact Statement, Draft Rules, other

Upon completion of AC membership approval memo

Lee

 

Director approval of AC membership

1 week after submittal from Goldstein

Whitman

 

Contact AC members to invite their participation; schedule AC meeting

Immediately on receiving director approval

Lee

 

Complete documents for AC meeting: Agenda, Fiscal Impact Statement, Draft Rules, other – submit for management review

3/28/19

Lee

 

Start drafting Notice of Rulemaking

On completion of AC document drafts

Lee

 

Management completes review and approves AC documents

4/11/19

Lee/OBrien/Emer/

Goldstein/Mills

 

AC documents posted on web –GovDelivery notice of meeting

4/15/19

Goldstein

 

Advisory Committee Meeting

4/22/19

Lee

 

Complete minutes of AC meeting; revise documents as necessary

4/29/19

Lee

 

Complete draft of Notice of Rulemaking – submit for management review

4/29/19

Lee

 

Notice of Rulemaking reviewed and approved by management

5/13/19

Lee/Goldstein/Obrien

Emer/Mills/Goldstein

 

Publish notice/open public comment period

5/15/19

Lee/Goldstein

 

Start drafting EQC staff report

5/15/19

Lee

 

Public hearing

6/14/19

Lee

 

Close comment period

6/17/19

Goldstein

 

Start drafting responses to comments and EQC staff report

6/17/19

Lee

 

Responses to comments and EQC staff report draft complete – submit for management review

6/20/19

Lee

 

EQC staff report review and approval by management complete

7/3/19

Lee/Obrien/Emer/

Mills/Goldstein

 

EQC staff report due to Caldera

7/11/19

Obrien/Lee/Goldstein

 

EQC Meeting

8/15/19

Obrien/Lee