Person | Task | Instructions | Date |
PL | Begin drafting EQC staff report | Notify Program Manager, Division Administrator, Communications, of dates below when they will receive documents to review -Develops response to comments by: Organizing comments into categories Developing one response to each category of comments Obtains PMGR and RGL review of draft responses Draft EQC staff report Copy and paste applicable sections from Public Notice into staff report Check to ensure language from Public Notice is still accurate and properly reflects timing of future/past events Edit rules as necessary Ask RGL for publication review | 5/15/18 |
PL | Complete draft staff report | Finalize proofing of EQC documents: Staff report Rules Supporting documents Notify RGL staff report is ready for review | 6/24/18 |
RGL | Preliminary staff report review | Prepare two versions of rules: redline/strikethrough clean Compare Notice with Staff Report for accuracy to check that language correctly reflects timing of future/past events | 6/26/18 |
PL | Send document links to PMGR for review | 6/28/18 | |
PMGR | Completes review and emails approval to PL | PMGR allowed one week to complete review | 7/5/2018 |
PL | On PMGR approval, provide document links to DA for review | 7/5/2018 | |
DA | Completes review and emails approval to PL PMGR RGL | DA allowed two calendar weeks to complete review | 7/19/2018 |
PL | On DA approval, provide document links to communications for review | 7/19/2018 | |
COM | completes review and emails approval to PL PMGR RGL | Communications allowed one calendar week to complete review | 7/26/2018 |
RGL | begins review | one week to complete review | 7/26/2018 |
RGL | Completes review | 8/2/2018 | |
PL/PMGR | (optional) discusses need for 1 on 1 commissioners briefings | ||
PL | DEADLINE TO SUBMIT FINAL VERSION OF ALL EQC DOCUMENTS | 6 weeks before EQC | 8/10/2018 |
RGL | Distribute EQC staff report and prepare rules for filing | Submits EQC packet to EQCC (EQC-5 weeks) Retain one copy of rules in redline/strikethrough for filing with legislative counsel Create a clean copy of the rules, with tables, to keep for informational purposes - add a DRAFT watermark Staff report should have two copies of rules - one showing all markup, one with DRAFT watermark with all changes accepted Remove tables from another copy of the rules, and accept all changes to get a clean copy of the rules to file with secretary of state Create pdf version of tables, one document for each rule that has a table, to submit to secretary of state Complete draft version (do not submit) of secretary of state online filing system using information from staff report and draft rules On SharePoint, publish a major version of: rules staff report Save PDF of published staff report to Rule_Development Upload copy of EQC presentation materials to SharePoint | 8/9/2018 |
PL | (Optional) Notify interested parties staff report is available | Notify the following according to division's standard practice: Key stakeholders Advisory committee members Commenters Interested parties | |
PL | EQC Preparation | Develop EQC presentation Conduct dry run EQC presentation (in front of internal audience) | |
PL | Present rule package at EQC MEETING | 9/13/2018 | |