ARC – Agency rules coordinator COM – Communications DA – Division administrator PL – Program lead PMGR – Program manager | |||
Person | Task | Instructions | Date |
• PL | • Begin drafting EQC staff report | Develops response to comments by: • Organizing comments into categories • Developing one response to each category of comments • Obtains PMGR and RGL review of draft responses • Draft EQC staff report • Copy and paste applicable sections from Public • Notice into staff report • Check to ensure language from Public Notice is still accurate and properly reflects timing of future/past events • Edit rules as necessary • Ask RGL for publication review | November 2016 |
• | • Submit EQC Packet to DEQ | LRAPA | November 2016 |
• PL | • Complete draft staff report | Finalize proofing of EQC documents: • Staff report • Rules • Supporting documents • Notify RGL staff report is ready for review | November 22, 2016 |
• ARC | • Review staff report, notify PL when complete | Lead initial Rule Publication work that includes: • Prepare two versions of rules: • redline/strikethrough • clean • Review, consolidate, approve or reject all proposed edits • Compare Notice with Staff Report for accuracy to check that language correctly reflects timing of future/past events • Notify PL review is complete | November 25, 2016 |
• PL | • Finalize EQC staff report (9 weeks before EQC) | • Address reviewer edits and comments • Notify PMGR staff report is ready for review | November 28, 2016 |
• PMGR | • Completes review and emails approval to PL | December 1, 2016 | |
• PL | • On PMGR approval ,notify DA documents are ready for review | ||
• DA | • Completes review and emails approval to PL PMGR RGL | December 4, 2016 | |
• PL | • On DA approval, notify communications documents are ready for review | • | |
• COM | • Completes review and emails approval to PL PMGR RGL (6 weeks before EQC) | December 7, 2016 | |
• PL | • Deadline to submit final version of all EQC documents (6 weeks before EQC) | December 7, 2016 | |
• ARC | • Distribute EQC staff report and prepare rules for filing | • Submits EQC packet to EQCC (EQC-5 weeks) • Retain one copy of rules in redline/strikethrough for filing with legislative counsel • Create a clean copy of the rules, with tables, to keep for informational purposes - add a DRAFT watermark • Staff report should have two copies of rules - one showing all markup, one with DRAFT watermark with all changes accepted • Remove tables from another copy of the rules, and accept all changes to get a clean copy of the rules to file with secretary of state • Create pdf version of tables, one document for each rule that has a table, to submit to secretary of state • Complete draft version (do not submit) of secretary of state online filing system using information from staff report and draft rules • On SharePoint, publish a major version of: • rules • staff report • Save PDF of published staff report to Rule_Development • Upload copy of EQC presentation materials to SharePoint | December 14, 2016 |
• PL | • (Optional) Notify interested parties staff report is available | Notify the following according to division's standard practice: • Key stakeholders • Advisory committee members • Commenters • Interested parties | |
• PL | • EQC Preparation | • Develop EQC presentation • Conduct dry run EQC presentation (in front of internal audience) | |
• PL | • Present rule package at EQC meeting | January 18, 2017 | |
• ARC | • | No Oregon deadline for filing rules after adoption – check EPA | |
• ARC | • File adopted rules with Secretary of State | • Check information in secretary of state online rule filing form against most recent information in staff report and draft rules • Submit/file rules on secretary of state online system • Must print out, sign, scan, then upload to SOS filing page, copy of Authorization • Upload rule text as Word file • Upload tables separately as pdf, one for each rule that has tables • SOS will auto email two documents in response in two separate emails: ◦ Certificate ◦ Authorization • Save the emails and attached documents as PDF to Rule_Development | January 21, 2017 |
• ARC | • Send post-EQC GovDelivery notice about rule adoption | • Template in EQC Preparation folder • RGL sends GovDelivery notice to same parties that prior notices for this rulemaking were sent to • This notice states EQC adopted the rules and explains where to find copies of EQC staff report and adopted rules | January 21, 2017 |
• ARC | • Submits SIP to EPA | • | January 25, 2017 |