A B C
1 What facilities have to do    
3 Tier 1 facilities    
4 deadline latest date action
5 9/1/2016 9/1/2016 apply for ACDP
6 - - DEQ issues ACDP
7 15 days before install begins 9/16/2016 submit Notice of Intent to Construct the baghouse
8 10 days after NOIC submitted 9/26/2016 DEQ gives permission to construct (permission is given by default if no DEQ response)
9 10/1/2016 10/1/2016 install baghouse
10 30 days before conducting the source test 10/31/2016 submit source test plan to DEQ
11 60 days after commencing operation of baghouse 11/30/2016 source test baghouse