What facilities have to do |
|
|
3 |
Tier 1 facilities |
|
|
4 |
deadline |
latest date |
action |
5 |
9/1/2016 |
9/1/2016 |
apply for ACDP |
6 |
- |
- |
DEQ issues ACDP |
7 |
15 days before install begins |
9/16/2016 |
submit Notice of Intent to Construct the baghouse |
8 |
10 days after NOIC submitted |
9/26/2016 |
DEQ gives permission to construct (permission is given by default
if no DEQ response) |
9 |
10/1/2016 |
10/1/2016 |
install baghouse |
10 |
30 days before conducting the source test |
10/31/2016 |
submit source test plan to DEQ |
11 |
60 days after commencing operation of baghouse |
11/30/2016 |
source test baghouse |