| A | B | C | |
|---|---|---|---|
| 1 | What facilities have to do | ||
| 3 | Tier 1 facilities | ||
| 4 | deadline | latest date | action |
| 5 | 9/1/2016 | 9/1/2016 | apply for ACDP |
| 6 | - | - | DEQ issues ACDP |
| 7 | 15 days before install begins | 9/16/2016 | submit Notice of Intent to Construct the baghouse |
| 8 | 10 days after NOIC submitted | 9/26/2016 | DEQ gives permission to construct (permission is given by default if no DEQ response) |
| 9 | 10/1/2016 | 10/1/2016 | install baghouse |
| 10 | 30 days before conducting the source test | 10/31/2016 | submit source test plan to DEQ |
| 11 | 60 days after commencing operation of baghouse | 11/30/2016 | source test baghouse |