1 Person Action Suggested Dates Amended Dates
2   CodeName (abbreviation) Start End Start End
4   Instructions        
6   Enter notice publication date under Suggested "Notice Published" Date        
7   Enter EQC date under Suggested "EQC Meeting" Date        
8   *Worksheet will populate dates under "Suggested Start Dates"
*If desired, manually fill in dates in "End" column
*Manually fill in desired dates under "Amended Dates"
*Find any term on sheet using control + F (find)
*"Summary" tab is overview of critical tasks and dates
       
10   Links to Task Headings        
12   Overview of Key Dates        
13   Concept Development        
14   Start Rulemaking        
15   Communications Planning        
16   Preplanning for Hearings        
17   EQC Facilitated Hearings        
18   Initial Rule Work        
19   Advisory Committee        
20   Fees        
21   Public Notice        
22   Rule Publication Work        
23   Preview Period        
24   Notifications        
25   Public Comment and Testimony        
26   Public Comment Closes        
27   EQC Preparation        
29   Abbreviations        
31 ARC Agency Rules Coordinator        
32 DA Division Administrator        
33 EQCC EQC Coordinator        
34 PL Program Lead        
35 RGL Rules Group Lead        
36 SIPC SIP Coordinator        
37 UMGR Unit Manager        
38 SP SharePoint        
39 Director DEQ Director        
40   Background        
42 Temporary or Permanent T/P        
43 Rule proposal complexity Simple/Average/Complex        
44 Advisory Committee Y/N        
45 Fees Y/N        
46 Fees- DAS approval required Y/N        
47 SIP Y/N        
48 EQC involvement before hearing Y/N        
49 EQC faciliated hearing? Y/N        
50   Overview of Key Dates        
52 Director Added to Rulemaking Plan        
53 PL SIP - submit SIP development plan to EPA (6 mos. before notice) 12/16/2014      
54 RGL/PL FEES - submit Part 1 of fee notice form to DAS (30 days before filing notice with SOS) 5/15/2015      
55 PL SIP - submit rule package to EPA (at least 90 days before notice) 3/16/2015      
56 PL Notice Packet due to RGL and UMGR for review 5/3/2015      
57 PL Notice Packet due to DA and Communications for review 5/17/2015      
58 RGL File notice with SOS/open comment period 6/14/2015      
59   Notice Published in Oregon Bulletin (DEQ standard 90 days before EQC) 7/1/2015      
60 PL first public hearing - at least 30 days AFTER comment opens; DEQ standard 17 days after Bulletin Notice published 7/18/2015      
61 RGL/PL close public comment - 3 days after hearing 7/21/2015      
62 PL Staff report due to EQCC (5 weeks before EQC) 9/9/2015      
63   EQC Meeting 10/14/2015      
64 RGL file rules        
65 Rules become effective On date filed or later specified date        
67 Director's report Director's Report        
68 Information item Information Item        
70   Rulemaking Process        
72   Concept Development        
74 UMGR contacts ARC about a potential rulemaking        
75 ARC explains add concept to plan process        
76 Unit manager approves completing Resources and Considerations worksheets        
77 ARC adds to Rules Idea list/workload spreadsheet        
78   establishes new Rule_Development folder system        
79   adds TEMPLATES to 1. Planning folder and adapts to concept: CONSIDERATIONS, RESOURCES, SCHEDULE        
80   Meets with PL to discuss completing workbooks        
81 PL With ARC help, drafts workbooks using what she or he knows now        
82 PL and UMGR Calculate rule priority based on DRIVERS and RISKS tables from Rulemaking SP page        
83 UMGR shares workbooks and prioritization info with DA        
84 UMGR emails DA approval or disapproval to ARC, UMGR, PL        
85 Units conduct internal rule prioritization process        
86 ARC Uses WORKBOOKS, DRIVERS and RISKS info to rank rulemaking on WORKLOAD spreadsheet        
87 Rules Group Meet and prioritize projects; create unitary agency-wide prioritized list        
88 Rules group resources prioritized projects        
89 ARC presents prioritized list to Director (3 times/yr.; Jan., May, Sept.)        
90 ARC adds prioritized, Director-aproved projects to agency rulemaking plan        
91 ARC notifies DA, PL, UMGR of Director's decision        
92   posts DEQ Rulemaking Plan on Rules and Regulations web page and Rulemaking SP page        
93   send draft notification email to Director for approval, include:
- Web page link
- DEQ Rulemaking Plan
- CONSIDERATIONS and RESOURCES Summary pages
       
94   after director approval, sends informational email to:
- Leadership Team
- all managers who make rules
- Communications
-EQC coordinator to include in monthly Director's Report
-Cc… DA, PL, RGL
       
96   Start Rulemaking        
98 ARC:          
99   saves email Rule_Development | 1-Planning | APPROVAL.ToMoveForward        
100   establishes SharePoint sub-site -simple email to web support (Michele T. - 4.2015)        
101   moves SCHEDULE from Rule_Development into SharePoint        
102   moves other workbooks from Rule_Development into SharePoint        
103 DA, UMGR, PL & RGL decide whether to expand team        
104 UMGR is responsible for:        
105   ·       getting new team members' manager approval        
106   ·       adding rulemaking to work plans as appropriate        
107 ARC gets Qtime number from ISS Fiscal Coordinator (Robert Beall 12.14)        
108 RGL drafts SCHEDULE and SUMMARY        
109 PL & RGL refine & agree on draft schedule        
110 PL schedules/holds team meeting(s) for consensus on:        
111   ·       RESOURCES workbook, identifies rulemaking and implementation need        
112   ·       CONSIDERATIONS workbook, reflects scope of work accurately        
113   ·       CONSIDERATIONS workbook identifies potential risks accurately        
114   ·       SCHEDULE of tasks and deadlines        
115 UMGR ensures program staff meets agreed upon dates in SCHEDULE        
117   Communications Planning        
119 PL schedules/facilitates meeting with team, Communications, Rules Group to discuss/determine need for: 2/14/2015      
120   ·       Communications Plan        
121   ·       Social Media        
122   ·       Message Map        
123   ·       Newspaper advertisements (SIP or local rulemaking only)        
124   ·       Newspaper release        
125   ·       Program Web page        
126   ·       Information Meetings before hearing        
127 RGL          
128   verifies Web content meets team expectations        
129   works with WebRep to make adjustments        
130 PL/RGL Publication Table:        
131   ·       identifies newspaper and publication date        
132   ·       develops an AD.STANDARD for each hearing if required        
133   ·       develops AD.LEGAL for each hearing if required        
134   ·       saves as NOTICE.AD.Hearing1, etc. on Rule_Development folder        
135   ·       determines when ADs need to be submitted to contractor        
136   ·       shares contents of HearingAndAdDates TAB with UMGR        
137   ·       obtains UMGR email approval        
139   Preplanning for Hearings (90 days before 1st hearing) 4/19/2015      
141 PL and RGL discuss requirements for hearings        
142 PL identifies hearing locations, dates and times        
143   Meeting 1 Location, Time        
144   Meeting 2 Location, Time        
145 PL reserves venues/equipment for hearings        
147   EQC Facilitated Hearings        
149 RGL and PL discuss requirements for EQC faciliated hearing        
150 PL observe EQC quorum notification requirements (ORS 192.630)        
151   identifies EQC facilitated hearing, coordinate with commissioner        
152   gathers all planning emails for the Rule Record and saves PDF to Rule_Development:|1-Planning|EMAILS.Planning.pdf        
154   Initial Rule Work (4 mos. Before filing notice) 2/17/2015      
156   DO NOT TURN OFF TRACK CHANGES IN CODENAME.RULES        
157 PL coordinates with Team to:        
158   ·       determine need for a crosswalk        
159   ·       identify rules to amend or repeal        
160   ·       identify new rules to adopt        
161   ·       identify land use rules        
162   ·       identify SIP rules, talk with SIP Coordinator        
163 RGL pulls rules to amend or repeal from SOS-Archives        
164   determines availability of any new (adopted) rule or division        
165   adds PROPOSED.RULES.Pristine template to Rule_Development        
166   copies subject rules from SOS into template        
167   saves PROPOSED.RULES.Pristine        
168   uploads a copy to SharePoint under Topic: Public Notice        
169   protects PROPOSED.RULES.Pristine on Rule_Development        
170   obtains, verifies, provides previously unused rule numbers        
171   shares information about rules that may be involved in other rulemakings        
172   performs 1st plain language, style guide edits on SharePoint        
173   offers organizational comments and examples        
174 PL leads rule writing on SharePoint CodeName.RULES to:        
175   ·       consider regulations, policies, programs and systems that may affect subject rules        
176   ·       validate/correct all citations, tables, formulas and document references within rule        
177   ·       validate/correct statutory authorities at bottom of each rule        
178   ·       validate/correct statutes implemented at bottom of each rule        
179   ·       validate/correct NOTE(s)        
180   ·       does not delete or change Hist. or ED.NOTES for any rule        
181   ·       SIP note is at bottom of all SIP rules and it is accurate        
182 All drafters and reviewers work on SharePoint Codename.RULES        
183 PL before submitting Notice Packet and EQC Packet:        
184   ·       verifies each rule in Codename.RULES is current with SOS compilation        
185   ·     verifies no rule adoptions could affect Codename.RULES        
187   Advisory Committee        
189 SAVE DOCUMENTS ON: SharePoint Topic: Public Notice        
190 DEADLINE: Notice committee meetings 2 weeks before meeting        
191 RGL          
192   Advisory Committee work session (120 days before meeting) 12/16/2014      
193   adapts Advisory Committee PowerPoint to rulemaking        
194   asks team to prepare for work session by reviewing:        
195   ·       advisory committee guidelines        
196   ·       Public Involvement Resources        
197   ·       EQC quorum notification requirements (ORS 192.630)        
198   ·       examples of the required Advisory Committee Web pages        
199   ·       optional committee AC.CHARTER        
200   ·       CONSIDERATIONS workbook in SharePoint Topic: Planning        
201   asks PL to prepare the following work session items:        
202   ·       add potential committee members to draft AC.ROSTER        
203   ·       list potential meeting dates and venues        
204   ·       draft AC.MEMBER.INVITATION        
205   ·       identify all GovDelivery topics that include affected parties        
206   ·       draft AC.AFFECTED.PARTIES.INVITATION to sign up for GovDelivery notices        
207   ·       draft AC.EQC.INVITATION to sign up for GovDelivery notices        
208   ·       draft AC.WebPage        
209   facilitates Advisory Committee work session that follows PowerPoint discussion and decision items        
210   discusses need to engage Communications (BrianW, Jennifer F.)        
211   decides whether to use optional AC.CHARTER Y/N        
212   advises PL on deliverables        
213 PL coordinates with team & UMGR for agreement on:        
214   ·       AC.WebPage        
215   ·       AC.CHARTER to include AC.ROSTER, meeting dates, venues        
216   ·       AC.MEMBER.INVITATION (includes URL and reminder to Sign-up        
217   ·       GovDelivery topic subscribers to get AC.AFFECTED.PARTIES.IN        
218   ·       AC.AFFECTED.PARTIES.INVITATION to sign up for GovDelivery        
219   ·       AC.EQC.INVITATION to sign up for GovDelivery notices        
220   ·       meeting dates and venues        
221            
222 UMGR and PL share Advisory Committee deliverables and decisions with DA        
223   team addresses any concerns and validates accuracy of how addressed        
224 UMGR approves deliverables including AC.ROSTER (90 days before meeting) 1/15/2015      
225 PL coordinates with team to:        
226   ·       talk with potential committee members to determine interest        
227   ·       finalize AC.ROSTER based on responses        
228 RGL works with WebRep to establish: 3/16/2015      
229   Advisory Committee page: http://www.oregon.gov/deq/RulesandRegulations/Pages/Advisory/A        
230   Advisory Committee meeting page: http://www.oregon.gov/deq/RulesandRegulations/Pages/Advisory/A        
231   Advisory Committee GovDelivery sign up        
233 PL identifies meeting roles        
234   coordinates or leads drafting:        
235   AC.AGENDA        
236   AC.GovDelivery.NOTICE        
237   AC.WebRequest.ATTACHMENT        
238   obtains team and UMGR input on agenda and GovDelivery notice        
239 RGL submits Web Request 2 weeks before meeting using AC.WebRequest 4/1/2015      
240   sends AC.GovDelivery.NOTICE to committee Web page        
241 PL releases unneeded venues        
243 UMGR, PL, RGL emails AC.MEMBER.INVITATION with links and instructions (60) days before meeting) to AC members 2/14/2015      
244   emails AC.EQC.INVITATION to sign up for Advisory Committee (min. 14 days before meeting) 4/1/2015      
245 RGL sends AC.AFFECTED.PARTIES.INVITATION to GovDelivery topic (min. 14 days before meeting) 4/1/2015      
246   submits Web Request when Advisory Committee Web page needs updating        
247 PL maintains Advisory Committee record        
249   Advisory Committee Presentation        
251 PL drafts optional AC.PRESENTATION        
252   involves stakeholder presenters, if any        
253 Team approves presentation materials        
254 RGL submits Web Request to post presentation materials        
255 Team practices presentation          
256 PL facilitates, leads or supports:        
257   Advisory Committee meeting (min. 60 days before filing notice) 4/15/2015      
258   drafting of AC.MINUTES        
259 team debrief meeting        
260 PL gathers all advisory committee emails for the Rule Record - in Rule_Development|3-FeesApproval|EMAILS.Fees.pdf        
262   Fees Involved - no action required for TEMPORARY rules        
264 PL leads development of: 4/15/2015      
265   Fee Approval Packet, with team and BudgetAnalyst        
266   a. FEE.ANALYSIS - SharePoint folder 3        
267   b. FEE.SUPPORT.DOCS        
268   c. FEE.APPROVAL        
269   d. FEE.DETAIL        
270   requests RGL's review for sufficiency, tone, plain language, (documents become part of Notice and EQC packets)        
271   initiates UMGR Fee Approval Packet review, addresses suggestions 5/1/2015      
274 RGL coordinates:        
275   sending EMAIL.DAS.APPROVAL with Fee Approval Packet attached (30 days before filing notice) 5/15/2015      
276   in Outlook, request delivery and read receipts        
277   save receipts to Rule_Development|3-Fee.Approval|PROOF.DAS.R        
278   DAS sends response to PL        
279   If denied, PL coordinates addressing DAS response        
280   If approved, PL scans and files DAS.PART1.pdf, DAS.PART1 used 7.Post EQC)        
281 PL gathers all fee emails for the Rule Record and saves in Rule_Development|3-FeesApproval|EMAILS.Fees.pdf        
283   Public Notice - not required for TEMPORARY rules        
284   (begin 90 days before filing notice) 3/16/2015      
285   SAVE DOCUMENTS ON:SharePoint Topic: Public Notice        
286   DO NOT TURN OFF TRACK CHANGES IN CODENAME.RULES        
287 PL leads core team in developing Notice Packet that includes:

-Codename.RULES SharePoint Topic: Public Notice
-NOTICE SharePoint Topic: Public Notice
-Overview
-Statement of Need
-Rules affected, authorities, supporting documents
-Fee Analysis
-Statement of fiscal and economic impact
-Federal relationship
-Land use
-Stakeholder and public involvement
-SUPPORTING.DOCS - optional SharePoint | 4 Public Notice
-INVITATION.TO.COMMENT (after Notice approved) SharePoint | 4 Public Notice
       
289   RESOURCE INPUT - THIS IS NOT A REVIEW        
291 PL asks RESOURCES for help and input, especially:        
292   RGL for process, organization, edits, plain language        
293   Affected staff, including regional staff, for subject matter        
294   SIP Coordinator for SIP consultation        
295   UMGR: for direction and subject consultation, especially to meet program goals for rulemaking, align with section, division and agency goals        
296   Communications (BrianW, Jennifer F.): for any updates to communication plan, message map, news release, social media        
297   ARC: for legal consultation and discuss need for AAG input        
298   Advisory Committee: for fiscal impact        
299 PL continually refines draft Notice Packet and considers RESOURCES input        
300   validates approach with staff who provided input        
301   asks AAG for input if needed & copies ARC on all AAG emails        
302   addresses legal concerns and discusses with UMGR as needed        
303   informs UMGR about the approach, issues and potential delays, raises unanticipated rulemaking and implementation risks to appropriate level        
304   informs RGL about potential delays and develop contingency, if needed        
305   asks contributors, including UMGR for consensus on subject completeness and accuracy        
307   Keep Management Informed        
309 PL determines with RGL and UMGR whether DA needs pre-publication review briefing        
310 PL asks DA Assistant to schedule future time on DA Schedule for briefing meeting (if necessary) with PL, UMGR and RGL        
311   asks DA Assistant to schedule future time on DA Schedule for reviewing notice package 4/26/2015      
312   schedules time on UMGR calendar to review Notice Package 4/26/2015      
313   verifies/adjusts previously scheduled briefing & review        
314   keeps UMGR informed about progress, risks & delays        
315 UMGR keeps management teams informed about progress        
317   Rule Publication Work        
319 PL prepares NOTICE, PROPOSED.RULES & optional SUPPORTING.DOCUMENTS        
320   addresses all comments, but does not delete them        
321   saves each document as Major version to capture all comments and tracked changes in NOTICE & optional SUPPORTING.DOCUMENTS:        
322   accepts and rejects language changes as team agrees        
323   ensures Word's track changes is turned on        
324   saves documents as Minor versions        
325   emails RGL for Rule Publication work when complete        
326 RGL determines whether NOTICE & SUPPORTING DOCUMENTS are ready for Rule Publication        
327 IF INCOMPLETE          
328   notifies UMGR who works with PL        
329   renegotiates schedule with UMGR & PL as needed        
330   reminds PL to reschedule managers' briefing if needed        
331   suspends Rule Publication work until PL resubmits documents        
332 IF COMPLETE          
333 PL asks RGL to apply CHECKLIST review to PROPOSED.RULES        
334 RGL leads review to determine fiscal and economic impact analysis sufficiency        
335   determines whether work products meet DEQ publication standards        
336 PL asks Communications, EQC Coordinator, ARC SIP Coordinator for input as needed        
337   discusses/resolves any editorial differences        
338   addresses input to ensure edits and comments speak with one voice        
339   accepts non substantive edits        
340   asks UMGR & PL for input/concurrence as needed        
341 UMGR, PL & RGL discuss:          
342   outstanding work        
343   need for AAG review        
344   need to renegotiate schedule        
345 PL          
346   addresses outstanding edits and comments        
347   asks AAG for review, if indicated, copies ARC and addresses input        
348   asks RGL & UMGR for concurrence on changes if indicated        
349   addresses outstanding edits and comments        
350   notifies RGL & UMGR when complete and ready for preview        
351 PL forwards notice package to UMGR for review (6 weeks before filing notice) 5/3/2015      
352 PL on UMGR approval, forwards notice package to DA for review        
353 DA completes review and emails approval to PL, UMGR, RGL        
355   Preview Period (leadership review) - 5-7 days        
357 RGL drafts EMAIL.PREVIEW (instructions in template)        
358 PL, UMGR Brief DA – only if necessary; controversial, complex, unusually challenging rulemaking        
359 RGL sends EMAIL.PREVIEW to:
-Director, DA, Leadership Team, EQCC
-Cc… all contributing and affected staff
-saves Email.Preview .pdf to Rule_Development - 4- Notice
5/31/2015      
360 PL. RGL, UMGR decide how to address any feedback from preview        
361 PL modifies documents as needed        
362 RGL verifies PROPOSED.RULES are still based on current compilation        
363 PL finalizes public documents with UMGR        
364 UMGR emails PL & RGL approval to move forward with NOTICE, PROPOSED.RULES & any SUPPORTING.DCUMENTS        
365 RGL saves email as Rule_Development | 4-Notice | MGR.APPROVAL.Notice.PDF        
366 PL/RGL drafts INVITATION.TO.COMMENT using information from approved NOTICE        
367 RGL establishes the following using Web Request:        
368   External Web page        
369   Online public comment form        
370   University Student Comment Account - helpdesk request with PL & RGL co-owning account; CodeName = “Alias”        
371   compares work products to earlier reviews to determine need for additional edits        
372   obtains additional Rule Publication edits on changes if needed        
373   verifies/clarifies additional edits with PL & UMGR as warranted        
374   notifies UMGR & PL when finished        
375   sets Outlook auto reply - instructions in Rulemaking Manual        
377   Notifications        
379 RGL/PL draft newspaper ads 5/19/2015      
380   send web request to create rulemaking, comment web pages 6/3/2015      
381 RGL drafts EMAIL.NOTICE.TO.KEY.LEGISLATORS - instructions in template        
382   sends draft to Leg.Liason        
383 Leg. Liason determines key legislators requiring ORS 183.335(5) notification        
384 RGL adapts email as needed        
385 RGL leads:        
386   submitting newspaper notices to contractor (14 days before filing notice- min. 30 days before hearing) 5/31/2015      
387   verifying newspaper advertisements are correct        
388   obtaining copies of affidavits of publication from Accounting        
389   adding hearings to DEQ Event Calendar        
390   creating an auto reply to Outlook account for University students        
391   validating Web page, comment form and Outlook account        
392   if no advisory committee, submit web request for rulemaking and comment web page 5/31/2015      
393 PL submits Notice to EPA, if required        
394 RGL submits notice to SOS for publication in Oregon Bulletin (not later than 15th of the month for publication the following month) 6/14/2015      
395   emails DAS notification of fees that don't require DAS approval        
396   saves all evidence on Rule_Development | 4-Notice using naming convention        
397   opens public comment by notifying agency rulemaking list that includes:        
398   GovDelivery        
399   EQCC        
400   advisory committee        
401   program-specific lists        
402   DEQ communications - publications and social media        
403   saves all evidence, lists and affidavits on Rule_Development | 4 Notice        
404 RGL emails Key Legislators with Return Receipt (redirects receipt to PL)        
405   copies PL        
406   saves receipts under Rule_Development|4-Notice        
407 RGL & WebRep maintain Rukemaking Web page        
408 PL gathers and saves all emails on Rule_Development|4-Notice using naming conventions        
410   Public Comment and Testimony        
412   Review version history to help maintaining rulemaking record        
413   SAVE DOCUMENTS ON: SharePoint Topic: Public Notice        
414 RGL meets with PL and Hearings Officers to discuss hearing procedures        
415 PL verifies venues and equipment, gathers supplies        
416   develops INFO.MEETING.TEXT        
417   modifies MESSAGE.MAP        
418   develops INFO.PRESENTATION        
419   practices presentation        
420   makes presentation adjustments        
421   initiates UMGR review/approval, addresses suggestions        
422 UMGR reviews/approves optional presentation        
423 Hearings Officers          
424   reviews responsibilities of hearings officer        
425   develops introductory and logistics script        
426   holds the following hearings (identified under Planning section) with assigned team        
427 Hearing 1 Location, Time 7/18/2015      
428   save audio as Rule_Development|5-PublicComment|HEARING.1.mp3        
429 PL for comments received by mail or at hearings:        
430   stamps DEQ receipt date on address-side of envelope and on first page of letter        
431   adds commenter and comment to COMMENTS        
432   scans mailed comments and envelopes and saves as ID###.pdf        
433   PUBLIC COMMENT CLOSES 7/21/2015      
434 RGL downloads online public comments to Excel, Codename.public.comment; save in Development | Public Comment and Testimony        
435   Downloads email comments from student email box to Excel; Codename.student.comment; save in Development | Public Comment and Testimony        
436 PL coordinates with team to:        
437   develop category titles to bundle similar comments        
438   organize comments into categories        
439   draft DEQ responses to each categories of comments        
440   leads team work finalizing DEQ responses to public comment        
441   DO NOT MAIL TO COMMENTERS UNTIL EQC ASSISTANT FINALIZES STAFF REPORT        
442 PL asks RGL for Rule Publication review        
443 RGL coordinates Rule Publication work:        
444   edits for plain English, style guide & tone because this is part of EQC packet        
445   contacts PL with questions, clarifications and suggestions        
446   notifies PL when complete        
447 PL shares comments/responses to comments with UMGR & DA        
448   team modifies responses to get to approval        
449 PL          
450   gathers emails ABOUT comments, not actual comments, for Rule Record        
451   saves them as Rule_Development|5-PublicComment...|EMAIL.Comment.pdf        
453   EQC Preparation        
455   Review version history to help maintaining rulemaking record        
456   SAVE DOCUMENTS ON: SharePoint TopicL EQC Preparation        
457 PL          
458   finalizes EQC Packet with core team:        
459   codename.staff.rpt        
460   codename.rules        
461   SUPPORTING.DOCUMENTS        
462   notifies RGL that EQC packet is ready for Rule Publication        
463 RGL leads initial Rule Publication work that includes:        
464   comparing NOTICE to STAFF.REPORT to determine what needs review        
465   obtaining/consolidating Communications, EQC Coordinator, SIP Coordinator edits, including style guide, grammar, plain English, organization        
466   accepting all style guide and format edits        
467   getting ARC review of PROPOSED.RULES- SOS/LC and CHECKLIST review        
468   contacts PL with questions or modifications and when work is complete        
469 PL          
470   addresses rule publication edits and comments        
471   prepares EQC packet        
472   initiates management review and approval: UMGR and DA 8/26/2015      
473   obtains approval from UMGR to submit EQC packet 9/2/2015      
474   discusses need for 1|1 commissioners briefings with UMGR/DA/EQCC        
475   submits EQC packet to EQCC (5 weeks before EQC) 9/9/2015      
476   notifies the following according to division's standard practice:        
477   ·       staff contributors        
478   ·       key stakeholders        
479   ·       advisory committee members        
480   ·       commenters        
481   ·       interested parties (optional)        
482   leads team development of EQC presentation        
483   coordinates presentation practices        
484   makes any presentation adjustments        
485 Presentation team ATTENDS EQC MEETING 10/14/2015      
486 PL saves emails about EQC preparations for Rule Record in Rule_Development|6-EQCPreparation|EMAILS.EQC.Prep.pdf        
488   Post EQC        
489 Review version history to help maintaining rulemaking record          
490   Document Preparation        
492 RGL saves following documents to 7.PostEQC folder on Rule_Develpment:        
493   gets documents as presented to EQC from EQC Coordinator        
494   STAFF.REPORT.pdf        
495   STAFF.REPORT.ADDENDUM.pdf (if presented to EQC)        
496   downloads documents as presented to EQC from SharePoint:        
497   PROPOSED.RULES (showing changes)        
498   saves as REDLINE.docx (showing changes in strikethrough and        
499   saves as RULES.docx (clean version), accepts all changes, saves again        
500   TABLES.340-###-####.docx (1 .docx per rule contains ALL tables)        
501   coordinates EPA.SIP.SUBMITAL with SIP Coordinator        
503   Filing        
505   DEADLINE: No Oregon deadline for filing rules after adoption - check EPA        
506 ARC          
507   logs onto Secretary of State online filing form        
508   uses information in STAFF.REPORT & ADDENDUM to populate form        
509   reviews, prepares and uploads:        
510   RULES.docx (clean version in Word)        
511   TABLES.340-###-####-SOS.pdf (1 .docx per rule contains ALL tables        
512   develops, scans and uploads AUTHORIZATION-SOS.pdf into online SOS form        
513   completes SOS form, verifies and submits        
514 Filed Date          
515 Effective Date          
516 ARC saves certificate that SOS sent via email as CERTIFICATE-SOS.pdf        
517   notes sequence for Certificate and Administrative Order No.        
518   submits Web request to update Web page        
519   moves share drive folder system:        
520   FROM: \\deqhq1\Rule_Development\Current        
521   TO: \\deqhq1\Rule_Development\Filed        
523   Legislative Counsel Notification        
524 DEADLINE LC must receive notification within 10 days after CERTIFICATE date        
525 DEQ PRACTICE Put in shuttle on day of SOS filing        
526 ARC          
527   prepares Legislative Counsel notification - see Rulemaking Manual:        
528 prints CERTIFICATE and saves copy as CERTIFICATE-LC.pdf        
529 prints REDLINE and saves copy as REDLINE-LC.pdf        
530   self-addressed envelope, fold underside of flap over a 2nd certificate        
531   write "Please date stamp certificate and return." on underside of flap        
532   prepares/scans return receipt shuttle envelope, saves as SHUTTLE.RECEIPT-LC.pdf        
533   sends via shuttle        
534   sends Procurement a scanned image of SHUTTLE.RECEIPT-LC        
535   DAS FEE APPROVAL - PART 2        
536 DEADLINE DEQ must send notification or DAS Part 2 within 10 days of EQC action        
537 PL          
538   gets signatures on Part 2 of signed DAS Fee Approval        
539   scans/saves as DAS.PART2.pdf        
540   excerpts fee sections from RULES, saves as FEE.RULES-DAS, print        
541   excerpts fee sections from STAFF.REPORT, saves as FEE.REPORT-DAS, print        
542   emails PART2-DAS.pdf to DAS (requests delivery receipt)        
543   get preprinted return receipt shuttle envelope from ARC        
544   prepares/scans shuttle envelope, saves as SHUTTLE.RECEIPT-DAS.pdf        
545   sends all fee documents to DAS via shuttle        
546   sends Procurement a scanned image of SHUTTLE.RECEIPT-DAS        
547   Closing Records and Archival        
549 RGL          
550   verifies Web page is current and accurate        
551   coordinates meeting to discuss lessons learned        
552   ensures the final version of every document on SharePoint is Major (Published)        
553   verifies Outlook student comment account is empty/asks helpdesk to close account        
554   leads verification that published rules in Oregon Bulletin are correct        
555   If errors, PL works with ARC to correct and selects        
556 SIPC submits SIP to EPA within 60 days AFTER adoption        
557   emails optional STAKEHOLDER.NOTIFICATION that links to Web page        
558   coordinates AC.THANK.YOU email or letter that links to Web page        
559   scans physical records and save to Rule_Development        
560   gathers emails about post EQC activities for the Rule Record and saves as: Rule_Development | 7-PostEQC | EMAILS.PostEQC.pdf        
561 ARC          
562   coordinates moving major versions from SharePoint to Rule_Development        
563   coordinates closing SharePoint sub-site        
564   archives folders when record is complete by moving:        
565   FROM: \\deqhq1\Rule_Development        
566   TO: \\deqhq1\Rule_Archives        
567   coordinates retiring Q-Time number(s) with BudgetAnalyst        

Schedule

  A B C D E F
1 Person Action __Suggested Dates_
|
Start | End
__Amended Dates__
|
Start | End
2   CodeName (abbreviated name)        
3   Abbreviations        
4 ARC Agency Rules Coordinator        
5 DA Division Administrator        
6 EQCC EQC Coordinator        
7 PL Program Lead        
8 RGL Rules Group Lead        
9 SIPC SIP Coordinator        
10 UMGR Unit Manager        
11 SP SharePoint        
12 Director DEQ Director        
13   Overview of Key Dates        
14 PL SIP - submit SIP development plan to EPA (6 mos. before notice) 12/16/2014      
15 PL SIP - submit rule package to EPA (at least 90 days before notice) 3/16/2015      
16 PL Notice Packet due to RGL and UMGR for review 5/3/2015      
17 PL Notice Packet due to DA and Communications for review 5/17/2015      
18 RGL File notice with SOS/open comment period 6/14/2015      
19   Notice Published in Oregon Bulletin (DEQ standard 90 days before EQC) 7/1/2015      
20 PL first public hearing - at least 30 days AFTER comment opens; DEQ standard 16 days after Bulletin Notice published 7/18/2015      
21 RGL/PL close public comment - 3 days after hearing 7/21/2015      
22 PL Staff report due to EQCC 7/21/2015      
23   EQC Meeting 10/14/2015      
24   Communications Planning        
25 PL schedules/facilitates meeting with team, Communications, Rules Group to discuss/determine need for:
-communications plan
-message map
-newspaper ads
-news release
-social media
-rulemaking/program web page
-informational meetings
2/14/2015      
26   Preplanning for Hearings (90 days before 1st hearing) 4/19/2015      
27   Initial Rule Work (4 mos. Before filing notice) 2/17/2015      
28 RGL and PL discuss requirements for EQC faciliated hearing        
29 PL coordinates with Team to:        
30 ·       determine need for a crosswalk        
31 ·       identify rules to amend or repeal        
32 ·       identify new rules to adopt        
33 ·       identify land use rules        
34 ·       identify SIP rules, talk with SIP Coordinator        
35   Advisory Committee (4 mos. before filing notice)        
36   Advisory Committee work session (120 days before meeting) 12/16/2014      
37 UMGR approves deliverables including AC.ROSTER (97 days before meeting) 1/15/2015      
38 UMGR, PL, RGL emails AC.MEMBER.INVITATION with links and instructions (60) days before meeting) 2/14/2015      
39 RGL, PL send web request to create rulemaking, advisory committee web pages 4/1/2015      
40   emails AC.EQC.INVITATION to sign up for Advisory Committee (min. 14 days before meeting) 4/1/2015      
41 RGL sends AC.AFFECTED.PARTIES.INVITATION to GovDelivery topic (min. 14 days before meeting) 4/1/2015      
42   Advisory Committee meeting (min. 60 days before filing notice) 4/15/2015      
43   Fees Involved - no action required for TEMPORARY rules        
44 PL leads development of: 4/15/2015      
45   Fee Approval Packet, with team and BudgetAnalyst        
46   a. FEE.ANALYSIS - SharePoint folder 3        
47   b. FEE.SUPPORT.DOCS        
48   c. FEE.APPROVAL        
49   d. FEE.DETAIL        
50   initiates UMGR Fee Approval Packet review, addresses suggestions 5/1/2015      
51 RGL coordinates:        
52   sending EMAIL.DAS.APPROVAL with Fee Approval Packet attached (30 days before filing notice) 5/15/2015      
53   Public Notice - not required for TEMPORARY rules
(begin 90 days before filing notice)
3/16/2015      
54 PL begin drafting rules and notice        
55   asks DA Assistant to schedule future time on DA Schedule for reviewing notice package        
56   schedules time on UMGR calendar to review Notice Package        
57   Rule Publication Work        
58 PL forwards notice package to UMGR for review (6 weeks before filing notice) 5/3/2015      
59 PL on UMGR approval, forwards notice package to DA for review        
60   Preview Period (leadership review) - 5-7 days        
61 RGL sends EMAIL.PREVIEW to:
-Director, DA, Leadership Team, EQCC
-Cc… all contributing and affected staff
-saves Email.Preview .pdf to Rule_Development - 4- Notice
5/31/2015      
62   Notifications        
63 RGL/PL draft newspaper ads 5/19/2015      
64   send web request to create rulemaking, comment web pages 5/19/2015      
65   submit newspaper notices to contractor (14 days before filing notice- min. 30 days before hearing) 5/31/2015      
66 RGL submits notice to SOS for publication in Oregon Bulletin (not later than 15th of the month for publication the following month) 6/14/2015      
67   Public Comment and Testimony        
68 Hearing 1 Location, Time 7/18/2015      
69   Public Comment Closes 7/21/2015      
70   EQC Preparation        
71   initiates management review and approval: UMGR and DA 8/26/2015      
72   obtains approval from UMGR to submit EQC packet 9/2/2015      
73   discusses need for 1|1 commissioners briefings with UMGR/DA/EQCC        
74   submits EQC packet to EQCC (5 weeks before EQC) 9/9/2015      
75 Presentation team ATTENDS EQC MEETING 10/14/2015      

summary