Scenario 1: December EQC Meeting |
|
|
|
|
|
|
|
Activity | Date | Notes |
|
|
|
|
|
Director's dialog | 8/21/2013 |
|
| ||||
End Advisory Committee meetings | Week of 8/26-8/29 | Recommendations report would need to be done quickly for notice | |||||
Notice packet ready for internal review | End of August |
|
| ||||
Notice packet approved | 9/9/2013 | Usually want 30 days of review, could do a quick 2 week review | |||||
Submit SOS notice | 9/13/2013 |
|
| ||||
SOS notice published | 10/1/2013 |
|
| ||||
EPA review and approval | 9/13-12/13/2013 | Expect to have to go through EPA Region 10 and HQ | |||||
Public hearings (3) | 10/16-10/22/2013 |
|
| ||||
Close public comment period | 10/31/2013 |
|
| ||||
Submit staff report | 11/1/2013 | Due 6 weeks prior to EQC, flexibility might be possible | |||||
Present EQC action item | 12/11/2013 |
|
| ||||
SOS - file rules | 12/13/2013 |
|
| ||||
Rules become effective | 12/13/2013 |
|
|
|
|
|
|
Scenario 2: January Special EQC Conference Call |
|
|
|
|
|
| |
Activity | Date | Notes |
|
|
|
|
|
Director's dialog | 8/21/2013 |
|
| ||||
End Advisory Committee meetings | Week of 8/26-29th or as scheduled for 9/5 |
|
| ||||
Notice packet ready for internal review | 9/11/2013 | Usually want 30 days of review, could do a quick 2 week review | |||||
Notice packet approved | 10/11/2013 |
|
| ||||
Submit SOS notice | 10/15/2013 |
|
| ||||
SOS notice published | 11/1/2013 |
|
| ||||
EPA review and approval | 10/15/2013-1/15/2014 | Expect to have to go through EPA Region 10 and HQ | |||||
Public hearings (3) | 11/18-11/26/2013 |
|
| ||||
Close public comment period | 12/2/2013 |
|
| ||||
Submit staff report | 11/29/2013 | Due 6 weeks prior to EQC, flexibility might be possible | |||||
Present EQC action item | 1/10/2014 |
|
| ||||
SOS - file rules | 1/14/2014 |
|
| ||||
Rules become effective | 1/14/2014 |
|
|
|
|
|
|
Highlighted activity notes challenging timeframe |