1 Scenario 1: December EQC Meeting      
2 Activity Date Notes  
3 Director's dialog 8/21/2013    
4 End Advisory Committee meetings Week of 8/26-8/29 Recommendations report would need to be done quickly for notice
5 Notice packet ready for internal review End of August    
6 Notice packet approved 9/9/2013 Usually want 30 days of review, could do a quick 2 week review
7 Submit SOS notice 9/13/2013    
8 SOS notice published 10/1/2013    
9 EPA review and approval 9/13-12/13/2013 EPA Region 10 and HQ approval could take 3-4+ months
10 Public hearings (3) 10/16-10/22/2013    
11 Close public comment period 10/31/2013    
12 Submit staff report 11/1/2013 Due 6 weeks prior to EQC, flexibility might be possible
13 Present EQC action item 12/11/2013    
14 SOS - file rules 12/13/2013    
15 Rules become effective 12/13/2013    
18 Scenario 2: January Special EQC Conference Call    
19 Activity Date Notes  
20 Director's dialog 8/21/2013    
21 End Advisory Committee meetings Week of 8/26-29th or as scheduled for 9/5    
22 Notice packet ready for internal review 9/11/2013 Usually want 30 days of review, could do a quick 2 week review
23 Notice packet approved 10/11/2013    
24 Submit SOS notice 10/15/2013    
25 SOS notice published 11/1/2013    
26 EPA review and approval 10/15/2013-1/15/2014 EPA Region 10 and HQ approval could take 3-4+ months
27 Public hearings (3) 11/18-11/26/2013    
28 Close public comment period 12/2/2013    
29 Submit staff report 11/29/2013 Due 6 weeks prior to EQC, flexibility might be possible
30 Present EQC action item 1/10/2014    
31 SOS - file rules 1/14/2014    
32 Rules become effective 1/14/2014    
34 Highlighted activity notes challenging timeframe      

Modified Schedule