| A | B | C | D | |
|---|---|---|---|---|
| 1 | Scenario 1: December EQC Meeting | |||
| 2 | Activity | Date | Notes | |
| 3 | Director's dialog | 8/21/2013 | ||
| 4 | End Advisory Committee meetings | Week of 8/26-8/29 | Recommendations report would need to be done quickly for notice | |
| 5 | Notice packet ready for internal review | End of August | ||
| 6 | Notice packet approved | 9/9/2013 | Usually want 30 days of review, could do a quick 2 week review | |
| 7 | Submit SOS notice | 9/13/2013 | ||
| 8 | SOS notice published | 10/1/2013 | ||
| 9 | EPA review and approval | 9/13-12/13/2013 | EPA Region 10 and HQ approval could take 3-4+ months | |
| 10 | Public hearings (3) | 10/16-10/22/2013 | ||
| 11 | Close public comment period | 10/31/2013 | ||
| 12 | Submit staff report | 11/1/2013 | Due 6 weeks prior to EQC, flexibility might be possible | |
| 13 | Present EQC action item | 12/11/2013 | ||
| 14 | SOS - file rules | 12/13/2013 | ||
| 15 | Rules become effective | 12/13/2013 | ||
| 18 | Scenario 2: January Special EQC Conference Call | |||
| 19 | Activity | Date | Notes | |
| 20 | Director's dialog | 8/21/2013 | ||
| 21 | End Advisory Committee meetings | Week of 8/26-29th or as scheduled for 9/5 | ||
| 22 | Notice packet ready for internal review | 9/11/2013 | Usually want 30 days of review, could do a quick 2 week review | |
| 23 | Notice packet approved | 10/11/2013 | ||
| 24 | Submit SOS notice | 10/15/2013 | ||
| 25 | SOS notice published | 11/1/2013 | ||
| 26 | EPA review and approval | 10/15/2013-1/15/2014 | EPA Region 10 and HQ approval could take 3-4+ months | |
| 27 | Public hearings (3) | 11/18-11/26/2013 | ||
| 28 | Close public comment period | 12/2/2013 | ||
| 29 | Submit staff report | 11/29/2013 | Due 6 weeks prior to EQC, flexibility might be possible | |
| 30 | Present EQC action item | 1/10/2014 | ||
| 31 | SOS - file rules | 1/14/2014 | ||
| 32 | Rules become effective | 1/14/2014 | ||
| 34 | Highlighted activity notes challenging timeframe | |||