Scenario 1: December EQC Meeting |
|
|
|
2 |
Activity |
Date |
Notes |
|
3 |
Director's dialog |
8/21/2013 |
|
|
4 |
End Advisory Committee meetings |
Week of 8/26-8/29 |
Recommendations report would need to be done quickly for notice |
5 |
Notice packet ready for internal review |
End of August |
|
|
6 |
Notice packet approved |
9/9/2013 |
Usually want 30 days of review, could do a quick 2 week review |
7 |
Submit SOS notice |
9/13/2013 |
|
|
8 |
SOS notice published |
10/1/2013 |
|
|
9 |
EPA review and approval |
9/13-12/13/2013 |
EPA Region 10 and HQ approval could take 3-4+ months |
10 |
Public hearings (3) |
10/16-10/22/2013 |
|
|
11 |
Close public comment period |
10/31/2013 |
|
|
12 |
Submit staff report |
11/1/2013 |
Due 6 weeks prior to EQC, flexibility might be possible |
13 |
Present EQC action item |
12/11/2013 |
|
|
14 |
SOS - file rules |
12/13/2013 |
|
|
15 |
Rules become effective |
12/13/2013 |
|
|
18 |
Scenario 2: January Special EQC Conference Call |
|
|
19 |
Activity |
Date |
Notes |
|
20 |
Director's dialog |
8/21/2013 |
|
|
21 |
End Advisory Committee meetings |
Week of 8/26-29th or as scheduled for 9/5 |
|
|
22 |
Notice packet ready for internal review |
9/11/2013 |
Usually want 30 days of review, could do a quick 2 week review |
23 |
Notice packet approved |
10/11/2013 |
|
|
24 |
Submit SOS notice |
10/15/2013 |
|
|
25 |
SOS notice published |
11/1/2013 |
|
|
26 |
EPA review and approval |
10/15/2013-1/15/2014 |
EPA Region 10 and HQ approval could take 3-4+ months |
27 |
Public hearings (3) |
11/18-11/26/2013 |
|
|
28 |
Close public comment period |
12/2/2013 |
|
|
29 |
Submit staff report |
11/29/2013 |
Due 6 weeks prior to EQC, flexibility might be possible |
30 |
Present EQC action item |
1/10/2014 |
|
|
31 |
SOS - file rules |
1/14/2014 |
|
|
32 |
Rules become effective |
1/14/2014 |
|
|
34 |
Highlighted activity notes challenging timeframe |
|
|
|