A B C D
1 January Special EQC Conference Call      
2 Activity Date Notes  
4 Director's dialog 8/21/2013    
6 End Advisory Committee meetings Week of 8/26-29th or as scheduled for 9/5    
11 Notice packet ready for internal review 9/11/2013 Usually want 30 days of review, could do a quick 2 week review
13 Notice packet approved 10/11/2013    
14 Submit SOS notice 10/15/2013    
16 SOS notice published 11/1/2013    
17 EPA review and approval 10/15/2013-1/15/2014 EPA Region 10 and HQ approval could take 3-4+ months
18 Public hearings (3) 11/18-11/26/2013    
19 Close public comment period 12/2/2013    
20 Submit staff report 11/29/2013 Due 6 weeks prior to EQC, flexibility might be possible
21 Present EQC action item 1/10/2014    
22 SOS - file rules 1/14/2014    
23 Rules become effective 1/14/2014    
25 Highlighted activity notes challenging timeframe      

Modified Schedule