Summary of Variance Examples
EXAMPLE FROM ARIZONA
Variance "Type": Individual variance issued to Central and Camelback Groundwater Treatment System Facility. The facility is extracting groundwater contaminated with tetrachloroethene (PCE) and BTEX and treating with granulated activated carbon units prior to discharge.
Pollutants: Boron (1,000 ug/L criterion associated with an Agricultural Designated Use)
Applicable Waterbody: Salt River Project Canal System
Applicable Duration: Five years
Attaining the Designated Use is Not Feasible Because:
40 CFR § 131.10(g)(1) - Naturally occurring pollutant concentrations prevent the attainment of the use. The facility operations do not contribute to the concentrations of boron naturally present in the source groundwater and receiving water.
Summary of Interim Conditions/Limits:
Maintain current discharge levels of boron during the term of the variance (<1300 ug/L).
History/Timeline:
Original Variance (<5 mos) |
September 28, 2007 | Arizona DEQ submits a request for the variance with supporting rationale to EPA. |
November 19, 2007 | EPA reviewed the request along with the associated draft permit that included a variance for boron and provided a preliminary approval of the variance, subject to public comment and review. |
February 14, 2008 | EPA approves the variance request. |
EXAMPLE FROM COLORADO
Variance "Type": Waterbody variance (referred to as a “temporary modification” in Colorado). Several POTWs discharge to the waterbody.
Pollutants: Copper (criteria associated with aquatic life designated use)
Applicable Waterbody: Monument Creek downstream of the Tri-Lakes Wastewater Treatment Facility
Applicable Duration: Three years
Attaining the Designated Use is Not Feasible Because:
Section 31.7(3)(a)(iii) of Colorado’s Basic Standards and Methodologies for Surface Waters (Basic Standards), authorizes temporary modifications where there is “significant uncertainty” regarding the appropriate long-term underlying standard. So, in this example, the Colorado Water Quality Control Commission adopted a temporary modification when results from the first two rounds of a water effects ratio (WER) study for copper indicated that development of site-specific aquatic life criteria for copper was justified. The temporary modification provides time for completion of the site-specific study.
Summary of Interim Conditions/Limits:
During the period of the temporary modification, acute and chronic criteria of 36.4 ug/L and 24.8 ug/L, respectively, apply to Monument Creek downstream of the Tri-Lakes Wastewater Treatment Facility. These interim criteria are equal to application of a WER of approximately 2 to the underlying criteria, which is conservative given that WERs of >5.2 and 7.3 were calculated in the first two rounds of WER testing.
History/Timeline:
Original Variance (<2 mos) |
November 9, 2004 | Colorado Water Quality Control Commission adopts the temporary modification. |
November 24, 2004 | EPA receives Colorado’s submission requesting approval of the temporary modification. |
January 2005 (approx. date) | EPA approves Colorado’s request for a temporary modification. |
EXAMPLE FROM IDAHO
Variance "Type": Individual variances issued to three municipal facilities
Pollutants: Cadmium, lead, and zinc (criteria associated with aquatic life designated use)
Applicable Waterbody: South Fork Coeur d'Alene River
Applicable Duration: Five years
Attaining the Designated Use is Not Feasible Because:
40 CFR § 131.10(g)(6) - Controls more stringent than those required by sections 301(b) and 306 of the Act would result in substantial and widespread economic and social impact
Summary of Interim Conditions/Limits:
Maintain current discharge levels during the term of the variance while working towards implementation of measures which will reduce metal concentrations over time. Specific requirements related to inflow and infiltration work and investigating treatment options included in the NPDES permits.
History/Timeline:
Original Issuance of Variances (< 3 yrs) |
2001 | Original exchanges between facilities and EPA pertaining to the need for and economic analysis conducted to support issuance of a variance. |
August 2002-January 2003 | EPA issues public notice for the variances and the draft permits incorporating the variances. |
August 1, 2004 | EPA incorporates variances into NPDES permits for the three facilities with a variance effective date of August 1, 2004, and expiration date of August 1, 2009. |
Variance Renewals (<7 mos) |
January 30, 2009/ February 19, 2009 | Idaho DEQ receives requests for variance renewals from the three facilities originally granted variances. |
April 1, 2009 | Idaho DEQ publishes a notice of the public comment period and public hearing on its tentative determination to grant variances for these three facilities (i.e., variance renewals). |
April 22, 2009 | Idaho DEQ holds a public hearing on its tentative determination. |
May 1, 2009 | Public comment period closes. |
June 12, 2009 | EPA receives Idaho DEQ's WQS submission for the three variance renewals. |
July 22, 2009 | EPA approves the variance renewals. |
EXAMPLE FROM MICHIGAN
Variance "Type": Multiple discharger variance (MDV) (may include either municipal or industrial permits)
Pollutants: Mercury (1.3 ng/L criterion associated with wildlife designated use)
Applicable Waterbody: Statewide
Applicable Duration: Five years
Attaining the Designated Use is Not Feasible Because:
40 CFR § 131.10(g)(6) - Controls more stringent than those required by sections 301(b) and 306 of the Act would result in substantial and widespread economic and social impact
Summary of Interim Conditions/Limits:
For reissuance of permits with reasonable potential and existing mercury limits:
• The mercury permit limit will be set at the facility-specific LCA (using MI’s mercury LCA calculation procedures) for the life of the permit.
• Require monitoring using Method 1631.
• Require a mercury pollutant minimization plan for the duration of the permit so that reasonable progress is made toward attaining the water quality standard.
• Use of a LCA that is calculated using some procedure other than MI’s mercury LCA calculation procedures will be evaluated by MDEQ on a case-by-case basis and submitted to EPA for review and approval.
For reissuance of permits with reasonable potential but without previous mercury limits:
• Monitor with Method 1631 monthly for two years of the permit.
• Set the mercury permit limit at the facility-specific LCA (using MI’s mercury LCA calculation procedures) effective at Year 3 (allow 2 years of monitoring before the limit takes effect).
• Require monitoring using Method 1631.
• Require a mercury pollutant minimization plan for the duration of the permit so that reasonable progress is made toward attaining the WQS.
• Use of a LCA that is calculated using some procedure other than MI’s mercury LCA calculation procedures will be evaluated by MDEQ on a case-by-case basis and submitted to EPA for review and approval.
For reissuance of permits with insufficient data for mercury limit determination:
• Require monthly monitoring with Method 1631 to start at permit issuance and continue for the permit duration.
• Include a Special Condition that triggers a mercury pollutant minimization plan if the monitoring data after one year indicates the presence of mercury at levels indicating reasonable potential to cause or contribute to exceedances of water quality standards.
• Evaluate the need for a permit modification to include a mercury limit, or include a mercury limit at the time of permit reissuance, if reasonable potential exists.
History/Timeline:
Original Variance (approx. 2 years) |
February 18, 2000 | Michigan DEQ submitted its Mercury Permitting Strategy, which incorporated a MDV for mercury, to EPA. The Strategy (applicable from 2000-2004) incorporated an interim level currently achievable (LCA) of 30 ng/L. |
May 24, 2002 | EPA approves MDV. |
Variance Renewal #1 (<2 mos) |
May 18, 2004 | Michigan DEQ submitted its revised Mercury Permitting Strategy, which incorporated a MDV for mercury, to EPA. The revised Strategy (applicable from 2005-2009) incorporated an interim LCA of 10 ng/L. |
June 29, 2004 | EPA approves the MDV. |
2004-2007 | EPA’s approval of the variance, particularly the uniform LCA of 10 ng/L, was challenged in federal court. |
November 30, 2007 | A settlement agreement in regards to the above-noted challenge was reached. |
September 5, 2008 | Michigan DEQ submits a revised procedure for calculating LCAs to EPA which replaced a component of the previously approved mercury MDV that established a statewide LCA of 10 ng/L. |
September 30, 2008 | EPA approves the methodology submitted to EPA on September 5, 2008, that Michigan will use to develop LCAs. |
Variance Renewal #2 |
August 17, 2009 | Michigan DEQ develops a DRAFT Multiple Discharger Variance for Mercury applicable for 2010-2014. |
EXAMPLE FROM TEXAS
Variance "Type": Individual variance issued to a municipal facility (City of Mount Pleasant)
Pollutants: Copper (criteria associated with aquatic life designated use)
Applicable Waterbody: Unnamed Tributary to Hart Creek
Applicable Duration: Three years
Attaining the Designated Use is Not Feasible Because:
Variances in Texas are provided when scientific information indicates that a site-specific standards adjustment is justified (see TX WQS at 30 TAC 307.2(d)(4)). So, in this example, the Texas Commission on Environmental Quality (TCEQ) granted a variance when results from the first round of a water effects ratio (WER) test for copper indicated that development of site-specific aquatic life criteria for copper was justified. The variance provides time for completion of the site-specific study.
Summary of Interim Conditions/Limits:
Any limits and monitoring/reporting requirements for the pollutant established under the previous permit are carried over into the new permit under the variance. Biomonitoring requirements are also included, as well as conditions to complete the associated site-specific criteria study, and a re-opener clause.
History/Timeline:
Original Variance (<4 mos) |
December 14, 2005 | Variance request submitted to TCEQ. |
December 16, 2006 | Internal TCEQ memo from WQS coordinator to NPDES permit writer recommending that the variance be granted. |
January 10, 2006 | Public notice for draft permit and variance is issued. |
March 10, 2006 | TCEQ submits request for approval of the variance from EPA. |
April 4, 2006 | EPA approves the variance (note – no effect determination made under ESA in this case) |
Post April 4, 2006 | Final NPDES permit issued |
EXAMPLE FROM WEST VIRGINIA
Variance "Type": Individual variance issued to an industrial facility (Union Carbide Corporation).
Pollutants: Chloride (criteria associated with aquatic life, recreation, and public water supply uses)
Applicable Waterbody: Entire length of Ward Hollow (approximately one mile) to where it enters Davis Creek
Applicable Duration: Two years
Attaining the Designated Use is Not Feasible Because:
40 CFR § 131.10(g)(1) - Naturally occurring pollutant concentrations prevent the attainment of the use. The facility operations do not contribute to the concentrations of boron naturally present in the source groundwater and receiving water.
To show that high chloride concentrations are naturally occurring in the Ward Hollow area, West Virginia and Union Carbide provided documentation showing that there are naturally occurring salt springs and deposits in the area.
Summary of Interim Conditions/Limits:
History/Timeline:
Original Variance (2 mos) |
July 26, 2006 | EPA receives the West Virginia Department of Environmental Protection’s submission requesting approval of the variance. |
September 26, 2006 | EPA approves the variance request. |
Variance Renewal (approx. 1 year) |
July 31, 2008 | West Virginia Department of Environmental Protection submits a request to EPA for approval of a variance renewal. |
September 8, 2009 | EPA approves the variance renewal request. |